Lake
Elsinore Wastewater Reclamation - CA |
|
Monksville Dam - NJ |
|
Project Cost: $50M |
|
Project Cost: $75M |
|
Services: Schedule
Delay & Damage Analysis |
|
Services: Schedule
Delay & Disruption Analysis |
|
|
|
|
|
Mohawk Water
Treatment Plant - AZ |
|
Jamaica WPCP - NY |
|
Project Cost: $100M |
|
Project
Cost: $150M |
|
Services:
Schedule Delay & Damage
Analysis |
|
Services:
Delay & Damage Analysis, Litigation Support |
|
|
|
|
|
Mendenhall Wastewater
Treatment Plant - AK |
|
Croton Water Treatment -
NY |
|
Project Cost: $150M |
|
Project Cost: $1.4B |
|
Services:
Schedule Delay Analysis; Change order Evaluation |
|
Services:
CPM Scheduling |
| |
|
|
|
Arlington/Chain
Bridge Water Project - VA |
|
Mt. Kisco Water
Treatment - NY |
|
Project Cost: $50M |
|
Project Cost: $20M |
|
Services: Evaluation & Preparation of Change Order
Requests |
|
Services:
Schedule Delay & Damage Analysis |
| |
|
|
|
Santa Teresa/Ricondada/Penetencia
WWTP - CA |
|
Bay Park STP - NY |
|
Project Cost: $150M |
|
Project
Cost: $200M |
|
Services:
Construction Audit; Pre-Construction Review |
|
Services:
Construction Management |
| |
|
|
|
Hale Avenue Water
Treatment Plant - CA |
|
Newtown Creek WPCP -
NY |
|
Project Cost: $75M |
|
Project
Cost: $250M |
|
Services:
Schedule Delay Analysis |
|
Services:
Change order Review & Value Analysis |
| |
|
|
|
Kent Wastewater
Treatment Plant - OH |
|
Bowery Bay WPCP - NY |
|
Project Cost: $75M |
|
Project
Cost: $500M |
|
Services:
Schedule Delay & Damage Analysis |
|
Services:
Schedule & Cost Analysis |
| |
|
|
|
Gowanus Canal
Rehabilitation - NY |
|
Great Neck STP - NY |
|
Project Cost: $120M |
|
Project
Cost: $10M |
|
Services:
Cost Estimating; Conceptual Scheduling |
|
Services:
Cost Estimating |
| |
|
|
|
Paerdegat Basin - NY |
|
Avenue V Pump Station
- NY |
|
Project Cost: $25M |
|
Project
Cost: $10M |
|
Services:
Schedule Review & Analysis; Cost Estimating |
|
Services:
Schedule & Cost Analysis |
| |
|
|
| |
|
|